Marina South Pier

Surbana Jurong was appointed to design and implement Marina South Pier as the replacement of the historic Clifford Pier in Singapore’s Central Business District.

The critical challenge was to devise a solution that would deal with the exposure of the area to waves and current movements, in order to have a year-round gateway for ferry shipping.

Our comprehensive approach enabled the completion of the project within 19 months, well ahead of the designated timeline. The project won numerous awards such as the SIA Architectural Award (2006), BCA Best Buildable Award (2007), BCA Design & Engineering Safety Excellence Award (2009) and BCA Construction Excellence Award (2009).

Completion of the project within 19 months,
well ahead of the designated timeline

SIA Architectural Award
in 2006


Country
Singapore

Service
Engineering & Specialist Services

滨海南码头

盛裕负责滨海南码头的设计和施工,该码头代替新加坡中心商务区之前的克利福码头。

为保证全年开放渡船运输,针对接触海浪和水流的区域设计方案是我们的主要挑战。

在我们的综合方案指导下,工程施工历时19个月,比规定时间大大提前。项目荣获2006年SIA建筑奖、2007年BCA最佳建筑奖、2009年BCA设计和工程安全卓越奖和2009年BCA建设卓越奖等多项大奖。

比规定时间大大提前
该项目施工历时19个月,

2006年
SIA建筑奖


Country
新加坡

Service
工程及特殊服务